At a glance
Late deliveries increased. To decide how to respond, the company reconstructed the history of two orders and the decisions that made the difference.
In an industrial company, the new Operations Director had been in the role for three months when he presented the quarterly results. On-time deliveries had declined. The chief executive had to decide whether to ask him to change the way he planned production, give him resources to clear the backlog or allow the new way of working more time.
The HR director asked to start with two orders. The first had been in difficulty even before the director joined, because a component was missing. The second had been accepted during the quarter with a delivery date the factory could meet only by postponing two other deliveries. They carried the same weight in the report. Reconstructing their history showed where the director had had room to act.
The order that was already late
When the director arrived, the supplier had already postponed the component’s shipment twice. The director arranged for someone to check whether an equivalent part was available and asked the warehouse which equipment was ready. The technical alternative would have taken longer than expected. Part of the order, however, was ready, and the salesperson agreed with the customer to dispatch it straight away.
The order still counted as late, because the promised date applied to the complete delivery. Reconstructing what had happened showed that the director had found a way to limit the disruption and that the customer had been able to use some of the equipment immediately.
The date promised without consulting the factory
A different problem emerged with the second order. The salesperson had confirmed the date with the customer before production checked the workload on the line. When the order reached the factory, keeping the promise meant rescheduling two orders that had already been confirmed.
After that episode, the director asked production to check the available hours for urgent orders before the salesperson confirmed delivery. At the end-of-quarter meeting, the HR director and the chief executive examined several orders that were similar in complexity and material availability. They wanted to understand whether the check had already changed any decisions. In one case, the line was again at full capacity. Having learnt this before responding to the customer, the salesperson proposed two partial deliveries. The customer agreed, and the other delivery dates remained unchanged.
What the chief executive decided
The chief executive countered that customers wanted to receive what they had been promised. One of them risked having to stop a production line and needed a firm delivery date by the following day. She therefore asked the director to prepare a recovery plan for the most urgent orders immediately.
The meeting also ended with a decision about new orders. The chief executive confirmed that delivery dates for urgent orders would be communicated after production had carried out its check. She scheduled a meeting for a month later to see, for those orders, how many dates had been met and how many had required other deliveries to be moved. If another delay put a customer’s production at risk, the director would let her know immediately.
Three questions to take to the meeting
When assessing the early results of someone who has taken on a new role, choose two important commitments and reconstruct a specific episode for each.
- What had already been decided or was already running into difficulties when the person joined?
- What decision did they make with the information and resources available to them? What happened next?
- What needs to be decided today, and what result do we want to check at the next meeting?